Construction paused at South Downtown station after crews hit a shallow water line near an underground parking area; work ...
Morning, y’all! If you don’t have kids and are wondering where all the traffic went this week, it’s spring break. I don’t have kids, and so I am constantly surprised by the changing school seasons. Oh ...
1d
Atlanta News First on MSNDiscovery of underground parking lot delays construction of Summerhill BRT lineThe route would connect downtown and Peoplestown through the Summerhill neighborhood. The route was supposed to launch this ...
1d
Rough Draft Atlanta on MSNMARTA's first bus rapid transit line won't open this year due to unexpected discoveriesMARTA’s first bus rapid transit line (BRT) connecting Downtown Atlanta to Summerhill, Peoplestown, and the Atlanta Beltline’s ...
A number of surprising underground discoveries — including a long-forgotten parking garage — have delayed the construction timeline for MARTA’s first rapid bus line.
The transit agency plans to resume the $230 million project on May 17, starting with the detour of Downtown bus routes. MARTA ...
The Metropolitan Atlanta Rapid Transit Authority will resume construction on its $230 million transformation of Five Points ...